Phase 4 Construction Projects
The era of 100 million passengers has begun.
Incheon International Airport now has the capacity to accommodate 106 million passengers and handle 6.3 million tons of cargo annually, thanks to the construction of a fourth runway and the expansion of the second passenger terminal, which were completed over a seven-year, four-phase construction project. With this framework established, we will adapt to shifts in the airport industry paradigm, enhance our future competitive advantage, and advance into the “Incheon Airport 4.0” era to create new value.
-
Number of flights Approx. 100,000 flights
-
Air Cargo 1.3million tons
-
Passenger Capacity 29million annually
Phase 4 Construction History
- Departure, Transfer: 11,150 bags/hr
- Arrival: 28,800 bags/hr
Phase 4 Construction OverView
Period | 2017.11.~2024.10.(84months) |
---|---|
Scale |
Terminal 2 347,000 ㎡ 1 Runway 62 Passenger Aprons, 13 Cargo Aprons |
Project Cost | KRW 4.8 trillion |
Major Milestones |
Nov. 13, 2017 Public Notice of an Amendment to the Basic Plan for Incheon International Airport Construction (4th Phase) Nov 01, 2018 Commencement of the construction for the fourth runway Nov. 01, 2019 Commencement of the expansion construction for terminal 2 |
Flight Processing Capacity | Capable of Handling Over 1,000 Flights Daily Per Annum |
Cargo Handling Capacity | 600,000 Flight Operations |
Cargo Handling Capacity | 6.3 million tons |
Passenger Handling Capacity | 106 Million |
Photo Gallery
list of postings
number | title | writing date | hits | attached file |
---|---|---|---|---|
7 | Terminal 2 | 2020.01.03 | 3 | |
6 | Traffic Center 2 (2013.6-2017.10) | 2020.01.03 | 0 | |
5 | Access roads | 2020.01.03 | 0 | |
4 | Passenger aprons | 2020.01.03 | 0 | |
3 | Baggage handling system | 2020.01.03 | 0 | |
2 | Connecting railroad | 2020.01.03 | 0 | |
1 | Apron Control Tower 2 | 2020.01.03 | 0 |
- Telephone : +082-32-741-2212, 2213
- Managing department : Airport Planning Team