Phase 2 Construction Projects
The Challenges for Incheon International Airport Never Cease.
Through the Phase 2 Construction Project, the Concourse, Runway 3, Cargo Terminal, and surrounding facilities were expanded. Such advancement transformed Incheon International Airport into a cutting-edge airport with world-class infrastructure, further positioning it as a hub airport representing not just Korea but all of Northeast Asia.
-
Flight Processing Capacity 100,000 flights annually
-
Air Cargo 0.5 million tons
-
Passenger Capacity 14 million annually
Phase 2 Construction History
Construction Period
77 Months
Project Cost (35% National Treasury)
KRW 2.9688 Trillion
Runways
1 (4,000×60 m)
Concourse
166,000 ㎡
Passenger Aprons
49 locations
Cargo Aprons
12 locations
Passenger Capacity
14 Million Passengers Annually
Cargo Handling Capacity
500,000 Tons Annually
Flight Processing Capacity
100,000 Flights Annually
Baggage Handling Capacity
(Concourse)
- Departure: 5,100 bags/hr
- Transfer: 4,590 bags/hr
- Arrival: 12,240 bags/hr
Parking Lot
1,079 spaces
Navigation Safety Facilities
CAT-lll a
Airport Railroad
Seoul Station ↔ Terminal 1 Double-track 59.3 km
Phase 2 Construction Overview
Period | January 2002–June 2008 (77 months) |
---|---|
Scale |
Concourse Area: 16,000 ㎡ 1 Third Runway1 Third Runway 49 Passenger Aprons, 12 Cargo Aprons |
Project Cost | KRW 2.9688 trillion |
Major Milestones |
June 28, 2004 - Start of Concourse Excavation and Piling Work Jul. 30, 2007 Completion of Paving for Runway 3 June 20, 2008 - Completion and Operation of Phase 2 Construction |
Annual Operation Handling Capacity | 170,000 Flights |
Cargo Handling Capacity | 1.8 Million Tons |
Annual Passenger Handling Capacity | 24 Million Passengers |
Airport Railroad | Seoul Station ↔ T1 Double-track, 61 km |