Phase 1 Construction Projects
In 1992, Yeongjong Island in the West Sea Was Transformed.
The construction of the breakwater and site work marked the beginning of an 8-year, 4-month long epic journey. The Phase 1 Construction Project was a grand endeavor that integrated all the advanced construction technologies possessed by Korea at the time. Through the construction of Terminal 1, Runways 1 and 2, aprons, and various auxiliary facilities, Incheon Airport proudly spread its wings towards becoming a global airport capable of competing with airports worldwide.
-
Flight Processing Capacity 330,000 flights annually
-
Air Cargo 4 million tons
-
Passenger Capacity 40 million annually
Phase 1 Construction History
Construction Period
101 Months
Project Cost (40% National Treasury)
KRW 5.6323 Trillion
Runways
2 (3,750×60 m)
Terminal 1
507,000 ㎡
Passenger Aprons
60 locations
Cargo Aprons
24 locations
Passenger Capacity
40 Million Passengers Annually
Cargo Handling Capacity
4 Million Tons Annually
Flight Processing Capacity
400,000 Flights Annually
Baggage Handling Capacity
(T1)
- Departure: 7,140 bags/hr
- Transfer: 4,590 bags/hr
- Arrival: 15,912 bags/hr
Transportation Center
250,000 ㎡
Parking Lot
16,591 Spaces
Navigation Safety Facilities
CAT-lll a
Airport Railroad
Land Acquisition and Partial Infrastructure
Phase 1 Construction OverView
Period | November 1992–March 2001 (101 months) |
---|---|
Scale |
Terminal 1 507,000 m² Runways 1 & 2 60 Passenger Aprons, 24 Cargo Aprons |
Project Cost | KRW 5.6323 trillionKRW 5.6323 trillion |
Major Milestones |
June 16, 1992 - Announcement of Metropolitan New Airport Construction Project May 23, 1996 - Commencement of Terminal 1 Construction March 29, 2001 - Incheon International Airport Opened |
Flight Processing Capacity | 330,000 flights annually |
Air Cargo Processing Capacity | 2.7 million tons |
Passenger Capacity | 30 million annually |
Airport Railroad | Land Acquisition, Partial Infrastructure |